Timeline of Events

Tracking the critical decisions, spending shifts, and construction progress over time.

Ad-Hoc Sub-Committee for the project receives a presentation on the proposed facility

Funding Approval

Project update for City Council

Project Milestone

City Council allocates $3,706,733 of ARPA (COVID-19) funding to the "Public Sector Revenue Loss Category"

Funding Approval

City Council approves the use of $18,500 in general funds to pay for an environmental review

Funding Approval

City Council approves up to $35M in lease revenue bonds for the PD HQ/RTC

Funding Approval

City Council approves a $882,925 contract with mack5 for project design and construction management

Contract Approval

City Council allocates a total of $7,413,467 in ARPA (COVID-19) funding to the "Public Sector Revenue Loss Category"

Funding Approval

City Council approves a $747,375 contract with LPA to create bridging documents

Funding Approval

Final presentation of conceptual designs given to City Council

Project Milestone

City Council approves using $5.4M of general funds to cover funding shortfall

Funding Approval

City Council allocates a total of $43.6M to the project

Funding Approval

City Council approves $38.5M contract with Overaa for design-build services

Contract Approval

Architectural plans submitted to the City

Project Milestone

Planning Commission approves a major design review

Project Milestone

City Council approves $169,468 increase in compensation to mack5

Contract Approval

City Council approves a contract up to $729,302 with Miles Treaster & Associates (MTA) for furniture for the facility

Contract Approval

City Council re-allocates $76,070.02 in ARPA funding to technology expenses for the project

Funding Approval

City Council decreases the budget by $470,000 and adds the interest from the Lease Revenue Bonds for a net increase of $1,920,325.

Funding Approval

Estimated completion date for the facility

Project Milestone